Hi Planning engineers and project managers! Like graphic designers, book authors, and any creative industry member, planning engineers and project managers should see work done by other engineers. Work done like xer file baseline by other planners.
Sometimes you spend many years at one company and learn its systematic way of doing time schedules and you don’t see schedules made by others. I think it is a healthy habit to see other work from other countries and cultures to see what other people are doing.
You may find them describing the activity names a better way, using activity coding or ID that may seem better for your future projects.
You may also find that they load the cost, resources, or BOQ in a better way.
That’s why I created this article. I collected 31 different time schedules for different types of projects.
From towers to residential to hospitals to factories to retail markets and airport halls. Different project has different requirements and needs, that’s making each project unique. You’ll learn a new thing from each project.
The list that I uploaded for you includes the following:
- Baseline schedule xer files
- hospital baseline xer time schedule
- detailed program xer template
- Oil & Gas time schedule xer file
- chocolate factory xer time schedule
- paper factory xer baseline
- residential compound baseline programme xer file
- retail store time schedule xer file
- airport terminal building xer baseline
- highway roads time schedule xer file
- more & more
All files are xer are files. You should download and install Primavera P6 here first to run them.